26INR0330 · BESS · Bexar County
Alamo City BESS
Alamo City BESS is a 128 MW battery storage project in Bexar County, Texas, connecting at Tap 138kV 5294 Martinez - 5110 JT Deely. ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 09/21/2027.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 26INR0330
- Capacity
- 128 MW
- Fuel
- BESS (BA)
- Substation
- Tap 138kV 5294 Martinez - 5110 JT Deely
- County
- Bexar County
- Interconnecting entity
- ALAMO CITY ESS LLC
- Projected COD
- 09/21/2027
- Entered queue
- 02/13/2024
- ERCOT zone
- SOUTH
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 08/21/2026FIS Requested → FIS Approved
- 05/22/2025FIS Approved → IA Signed
- 02/13/2024Entered the queue with 128 MW, projected COD 09/21/2027
- 02/13/2024Screening → FIS Requested