27INR0393 · BESS · Bexar County
Ferdinand Grid BESS II
Ferdinand Grid BESS II is a 208 MW battery storage project in Bexar County, Texas, connecting at 5260 Leon Creek 138kV. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 12/01/2027.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 27INR0393
- Capacity
- 208 MW
- Fuel
- BESS (BA)
- Substation
- 5260 Leon Creek 138kV
- County
- Bexar County
- Interconnecting entity
- Coval Infrastructure DevCo LLC
- Projected COD
- 12/01/2027
- Entered queue
- 12/03/2024
- ERCOT zone
- SOUTH
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 12/03/2024Entered the queue with 208 MW, projected COD 12/01/2027
- 12/03/2024Screening → FIS Requested