LoneStarGrid
ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
28INR0024 · BESS · Bexar County

Padua Grid BESS Unit 3

Padua Grid BESS Unit 3 is a 201 MW battery storage project in Bexar County, Texas, connecting at Tap #5395 O.W Sommer 138kV. ERCOT's October 2026 report shows it at the Sync Approved stage with a projected commercial operation date of 05/15/2026.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
28INR0024
Capacity
201 MW
Fuel
BESS (BA)
Interconnecting entity
Padua Grid 3, LLC
Projected COD
05/15/2026
Entered queue
03/01/2024
ERCOT zone
SOUTH
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 06/22/2026
    Energization Approved → Sync Approved
  • 06/12/2026
    IA Signed → Energization Approved
  • 06/20/2025
    FIS Requested → FIS Approved
  • 03/07/2025
    FIS Approved → IA Signed
  • 03/01/2024
    Entered the queue with 201 MW, projected COD 05/15/2026
  • 03/01/2024
    Screening → FIS Requested

Other projects at this substation