ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
24INR0392 · BESS · Bexar County

Riverwalk BESS

Riverwalk BESS is a 120 MW battery storage project in Bexar County, Texas, connecting at 5294 Martinez Substation 138kV. ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 10/01/2027.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
24INR0392
Capacity
120 MW
Fuel
BESS (BA)
Interconnecting entity
RWE Solar Developement, LLC
Projected COD
10/01/2027
Entered queue
07/11/2022
ERCOT zone
SOUTH
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 08/18/2026
    FIS Requested → IA Signed
  • 07/11/2022
    Entered the queue with 120 MW, projected COD 10/01/2027
  • 07/11/2022
    Screening → FIS Requested

Other projects at this substation

No other projects at this substation.