LoneStarGrid
ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
Counties / Texas

Webb County power projects

Webb County, Texas has 19 active power projects totalling 4,271 MW in ERCOT's interconnection queue as of the October 2026 report. Battery storage is the largest share at 1,644 MW (38%). The largest single project is Outpost Storage (508 MW battery storage). 6 projects have signed an interconnection agreement or reached a later stage. 1 project in the county is listed as withdrawn or cancelled.

Active projects
19
4.3 GW capacity
IA signed or later
6
32% of active projects
Withdrawn or cancelled
1
listed by ERCOT
Changes tracked
1
since Sep 2026

Changes in Webb County

Stage change
09/28/2026
Cenizo Solar · Solar · Webb County
Moved from FIS Requested to IA Signed.
IA Signed

All projects

ProjectFuelMWSubstationStageCOD
Outpost StorageBESS508345kv Avanzada7A (80235)FIS Requested03/01/2028
SieteWind493345kV 8718 TriadaIA Signed03/31/2029
Siete WindWind493345kV 8718 TriadaFIS Requested01/03/2028
Cuchillas BESSBESS30780219 Lobo 345kVFIS Requested12/15/2028
Cuchillas SolarSolar30680219 Lobo 345kVIA Signed12/15/2028
Cenizo SolarSolar301Tap 345 kV 80220 Cenizo - 80079 Cruce Ckt 2IA Signed12/31/2029
Diamond Sage Solar 1Solar214tap 345kV 80219 LOBO7A - 5709 FOWLERFIS Requested10/01/2028
Diamond Sage Solar 2Solar214Tap 345kV LOBO7A (80219) - FOWLERTONSW5 (5709)FIS Requested10/01/2028
Bravo BESSBESS207Tap 345kV 80220 CENIZO7A - 80224 TIEMPO7AFIS Requested12/12/2027
Corazon Solar Phase IISolar20480219 Lobo 345kVIA Signed06/01/2028
Corvus SolarSolar202Tap 345kV Cenzio (#80219) - Lobo (#80220)IA Signed11/12/2028
El Molino Solar SLFSolar201Tap 138kV 80439 LaQuinta - 8297 Bruni 8297FIS Requested09/01/2029
Pradera StorageBESS153tap 345 kV Lobo 80219 - Fowlerton 5709 ckt #2FIS Requested06/23/2029
Becerra Creek Storage 1BESS126345 kV Cenizo Substation (#80220)FIS Requested12/01/2027
Becerra Creek Storage 2BESS126345 kV Cenizo Substation (#80220)FIS Requested12/01/2027
Diamond Sage BESS 1BESS104tap 345kV 80219 LOBO7A - 5709 FOWLERTONSW5 CKT2FIS Requested10/01/2028
Diamond Sage BESS 2BESS104Tap 345kV LOBO7A (80219) - FOWLERTONSW5 (5709)FIS Requested10/01/2028
Torrecillas BESSBESS10161257 Torrecillas 345kVSync Approved12/31/2026
El Molino Storage SLFBESS0Tap 138kV 80439 LaQuinta - 8297 Bruni 8297FIS Requested09/01/2029
Pluto SolarSolar228Not listedWithdrawnn/a

For residents and landowners

What power projects are planned in Webb County?
ERCOT's October 2026 report lists 19 active projects in Webb County totalling 4,271 MW. The table on this page lists each one with its fuel type, size, substation and stage.
Where do these projects connect to the grid?
Each project names a point of interconnection, usually a substation or a tap on a transmission line. Land near those points is where developers look for sites.
What does "IA Signed" mean?
The developer has signed an interconnection agreement with the transmission owner. It is one of the strongest signs in the queue that a project may be built, though projects can still withdraw.
When would construction start?
Usually 12 to 24 months before the projected commercial operation date (COD). CODs often move later; each project page shows how many times its COD has changed.
Does a project in the queue mean it will be built?
No. Many queued projects are never built. The queue shows requests to connect, not approved construction. County permits, tax agreements and financing are separate steps.