22INR0257 · Solar · Webb County
Corazon Solar Phase II
Corazon Solar Phase II is a 204 MW solar project in Webb County, Texas, connecting at 80219 Lobo 345kV. ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 06/01/2028.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 22INR0257
- Capacity
- 204 MW
- Fuel
- Solar (PV)
- Substation
- 80219 Lobo 345kV
- County
- Webb County
- Interconnecting entity
- BAYWA R.E. SOLAR PROJECTS
- Projected COD
- 06/01/2028
- Entered queue
- 12/04/2019
- ERCOT zone
- SOUTH
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 08/04/2020FIS Requested → IA Signed
- 12/04/2019Entered the queue with 204 MW, projected COD 06/01/2028
- 12/04/2019Screening → FIS Requested
Other projects at this substation
| Cuchillas Solar | Solar | 306 MW | IA Signed |
| Cuchillas BESS | BESS | 307 MW | FIS Requested |