Substation / point of interconnection ยท Webb County
345kv Avanzada7A (80235)
1 active project totalling 508 MW is queued to connect at 345kv Avanzada7A (80235) in Webb County, Texas, according to ERCOT's October 2026 report.
Active capacity
508 MW
queued at this substation
Active projects
1
1 project ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
345 kV
read from the name
Projects at this substation
| INR | Project | Fuel | MW | Stage | COD | Delays |
|---|---|---|---|---|---|---|
| 23INR0209 | Outpost Storage | BESS | 508 | FIS Requested | 03/01/2028 | 0 |