LoneStarGrid
ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
27INR0414 · BESS · Webb County

Diamond Sage BESS 1

Diamond Sage BESS 1 is a 104 MW battery storage project in Webb County, Texas, connecting at tap 345kV 80219 LOBO7A - 5709 FOWLERTONSW5 CKT2. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 10/01/2028.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
27INR0414
Capacity
104 MW
Fuel
BESS (BA)
Interconnecting entity
DGC Renewables, LLC
Projected COD
10/01/2028
Entered queue
01/27/2025
ERCOT zone
SOUTH
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 01/27/2025
    Entered the queue with 104 MW, projected COD 10/01/2028
  • 01/27/2025
    Screening → FIS Requested

Other projects at this substation

No other projects at this substation.