27INR0390 · Solar · Webb County
Diamond Sage Solar 1
Diamond Sage Solar 1 is a 214 MW solar project in Webb County, Texas, connecting at tap 345kV 80219 LOBO7A - 5709 FOWLER. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 10/01/2028.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 27INR0390
- Capacity
- 214 MW
- Fuel
- Solar (PV)
- Substation
- tap 345kV 80219 LOBO7A - 5709 FOWLER
- County
- Webb County
- Interconnecting entity
- DGC Renewables, LLC
- Projected COD
- 10/01/2028
- Entered queue
- 01/27/2025
- ERCOT zone
- SOUTH
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 01/27/2025Entered the queue with 214 MW, projected COD 10/01/2028
- 01/27/2025Screening → FIS Requested