Corvus Solar

Corvus Solar is a 202 MW solar project in Webb County, Texas, connecting at Tap 345kV Cenzio (#80219) - Lobo (#80220). ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 11/12/2028.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
27INR0126
Capacity
202 MW
Fuel
Solar (PV)
Interconnecting entity
Corvus Solar, LLC
Projected COD
11/12/2028
Entered queue
01/16/2024
ERCOT zone
SOUTH
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 08/31/2026
    FIS Requested → FIS Approved
  • 07/31/2025
    FIS Approved → IA Signed
  • 01/16/2024
    Entered the queue with 202 MW, projected COD 11/12/2028