Kaufman County power projects

Kaufman County, Texas has 16 active power projects totalling 2,075 MW in ERCOT's interconnection queue as of the October 2026 report. Solar is the largest share at 1,102 MW (53%). The largest single project is Solarville Solar SLF (403 MW solar). 4 projects have signed an interconnection agreement or reached a later stage. 2 projects in the county are listed as withdrawn or cancelled.

Active projects
16
2.1 GW capacity
IA signed or later
4
25% of active projects
Withdrawn or cancelled
2
listed by ERCOT
Changes tracked
0
since Sep 2026

Changes in Kaufman County

No changes in the reports compared so far.

All projects

ProjectFuelMWSubstationStageCOD
Solarville Solar SLFSolar403Tap 345kV #3123 Trinidad Switch – #2432 Tri Corner.FIS Requested07/01/2029
Mystic Springs Renewable Energy Solar SLFSolar259Tap 345 kV Royse Switch (2478) – Poetry Switch (2485)IA Signed03/31/2028
Sowers StorageBESS2096894 Rose Hill_RC Sub 138 kVIA Signed07/01/2027
Yellow Leaf II BESSBESS206Tap 138kV 2727 CRANDALL1_8 - 2724 KAUFMN_8FIS Requested09/25/2028
Erika SolarSolar200Tap 345kV ELKTON 5 (#3105 ) to Tricrn1 5 (#2432)Sync Approved11/25/2026
Slash Pine StorageBESS2001698 Sulphur Springs Switch and 3174 Canton Switch 138 kVFIS Requested09/17/2029
Fudge Ranch BESSBESS1046902 TALTY_RC 138kVFIS Requested06/30/2027
Yellow Leaf SolarSolar103Tap 138kV Crandall (#2727) – Kaufman Northwest (#2724)FIS Requested09/25/2028
Yellow Leaf BESSBESS103Tap 138kV Crandall (#2727) – Kaufman Northwest (#2724)FIS Requested09/25/2028
Erika BESSBESS100Tap 345kV ELKTON 5 (#3105 ) to Tricrn1 5 (#2432)FIS Requested07/01/2029
Sunbelt SolarSolar82tap 138kV 6902 Talty - 6801 PattonFIS Requested12/31/2026
LUBIO SOLARSolar55tap 138kV 2727 Crandall - 2724 Kaufman NorthwestIA Signed04/20/2028
Sunbelt StorageBESS52Tap 138kV 6902 Talty - 6894 Rose HillFIS Requested12/31/2026
Mystic Springs Renewable Energy Storage SLFBESS0Tap 345 kV Royse Switch (2478) – Poetry Switch (2485)FIS Approved03/31/2028
Solarville Wind SLFWind0Tap 345 kV (#2432)Tri Corner - (#3105) ElktonFIS Requested09/19/2028
Solarville BESS SLFBESS0Tap 345 kV (#2432)Tri Corner - (#3105) ElktonFIS Requested09/19/2028
Tempesta BESSBESS600Not listedWithdrawnn/a
TempestaSolar443Not listedWithdrawnn/a

For residents and landowners

What power projects are planned in Kaufman County?
ERCOT's October 2026 report lists 16 active projects in Kaufman County totalling 2,075 MW. The table on this page lists each one with its fuel type, size, substation and stage.
Where do these projects connect to the grid?
Each project names a point of interconnection, usually a substation or a tap on a transmission line. Land near those points is where developers look for sites.
What does "IA Signed" mean?
The developer has signed an interconnection agreement with the transmission owner. It is one of the strongest signs in the queue that a project may be built, though projects can still withdraw.
When would construction start?
Usually 12 to 24 months before the projected commercial operation date (COD). CODs often move later; each project page shows how many times its COD has changed.
Does a project in the queue mean it will be built?
No. Many queued projects are never built. The queue shows requests to connect, not approved construction. County permits, tax agreements and financing are separate steps.