LoneStarGrid
ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
27INR0456 · BESS · Kaufman County

Yellow Leaf BESS

Yellow Leaf BESS is a 103 MW battery storage project in Kaufman County, Texas, connecting at Tap 138kV Crandall (#2727) – Kaufman Northwest (#2724). ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 09/25/2028.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
27INR0456
Capacity
103 MW
Fuel
BESS (BA)
Interconnecting entity
Lightsource Renewable Energy Development LLC
Projected COD
09/25/2028
Entered queue
03/14/2025
ERCOT zone
NORTH
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 03/14/2025
    Entered the queue with 103 MW, projected COD 09/25/2028
  • 03/14/2025
    Screening → FIS Requested

Other projects at this substation

Yellow Leaf SolarSolar103 MWFIS Requested