Yellow Leaf II BESS
Yellow Leaf II BESS is a 206 MW battery storage project in Kaufman County, Texas, connecting at Tap 138kV 2727 CRANDALL1_8 - 2724 KAUFMN_8. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 09/25/2028.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 28INR0412
- Capacity
- 206 MW
- Fuel
- BESS (BA)
- County
- Kaufman County
- Interconnecting entity
- Yellow Leaf Energy Storage LLC
- Projected COD
- 09/25/2028
- Entered queue
- 07/18/2025
- ERCOT zone
- NORTH
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 07/18/2025Entered the queue with 206 MW, projected COD 09/25/2028
- 07/18/2025Screening → FIS Requested