LoneStarGrid
ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
22INR0552 · BESS · Kaufman County

Sowers Storage

Sowers Storage is a 209 MW battery storage project in Kaufman County, Texas, connecting at 6894 Rose Hill_RC Sub 138 kV. ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 07/01/2027.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
22INR0552
Capacity
209 MW
Fuel
BESS (BA)
Interconnecting entity
Sowers Energy Storage LLC
Projected COD
07/01/2027
Entered queue
08/18/2021
ERCOT zone
NORTH
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 04/22/2022
    FIS Requested → IA Signed
  • 08/18/2021
    Entered the queue with 209 MW, projected COD 07/01/2027
  • 08/18/2021
    Screening → FIS Requested

Other projects at this substation

No other projects at this substation.