24INR0339 · Solar · Kaufman County
Mystic Springs Renewable Energy Solar SLF
Mystic Springs Renewable Energy Solar SLF is a 259 MW solar project in Kaufman County, Texas, connecting at Tap 345 kV Royse Switch (2478) – Poetry Switch (2485). ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 03/31/2028.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 24INR0339
- Capacity
- 259 MW
- Fuel
- Solar (PV)
- County
- Kaufman County
- Interconnecting entity
- Mystic Spring Renewable Energy LLC
- Projected COD
- 03/31/2028
- Entered queue
- 05/10/2022
- ERCOT zone
- NORTH
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 10/30/2025FIS Approved → IA Signed
- 04/17/2025FIS Requested → FIS Approved
- 11/28/2022Screening → FIS Requested
- 05/10/2022Entered the queue with 259 MW, projected COD 03/31/2028
Other projects at this substation
| Mystic Springs Renewable Energy Storage SLF | BESS | 0 MW | FIS Approved |