Mystic Springs Renewable Energy Storage SLF

Mystic Springs Renewable Energy Storage SLF is a 0 MW battery storage project in Kaufman County, Texas, connecting at Tap 345 kV Royse Switch (2478) – Poetry Switch (2485). ERCOT's October 2026 report shows it at the FIS Approved stage with a projected commercial operation date of 03/31/2028.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
24INR0340
Capacity
0 MW
Fuel
BESS (BA)
Interconnecting entity
Mystic Spring Renewable Energy LLC
Projected COD
03/31/2028
Entered queue
05/10/2022
ERCOT zone
NORTH
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 04/17/2025
    FIS Requested → FIS Approved
  • 11/28/2022
    Screening → FIS Requested
  • 05/10/2022
    Entered the queue with 0 MW, projected COD 03/31/2028