Substation / point of interconnection · Kaufman County
Tap 345kV #3123 Trinidad Switch – #2432 Tri Corner.
1 active project totalling 403 MW is queued to connect at Tap 345kV #3123 Trinidad Switch – #2432 Tri Corner. in Kaufman County, Texas, according to ERCOT's October 2026 report.
Active capacity
403 MW
queued at this substation
Active projects
1
1 project ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
345 kV
read from the name
Projects at this substation
| INR | Project | Fuel | MW | Stage | COD | Delays |
|---|---|---|---|---|---|---|
| 26INR0086 | Solarville Solar SLF | Solar | 403 | FIS Requested | 07/01/2029 | 0 |