ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
Counties / Texas

Howard County power projects

Howard County, Texas has 17 active power projects totalling 2,480 MW in ERCOT's interconnection queue as of the October 2026 report. Battery storage is the largest share at 1,659 MW (67%). The largest single project is Infinium Solar (402 MW solar). 2 projects have signed an interconnection agreement or reached a later stage. 0 projects in the county are listed as withdrawn or cancelled.

Active projects
17
2.5 GW capacity
IA signed or later
2
12% of active projects
Withdrawn or cancelled
0
listed by ERCOT
Changes tracked
0
since Sep 2026

Changes in Howard County

No changes in the reports compared so far.

All projects

ProjectFuelMWSubstationStageCOD
Infinium SolarSolar402#1058 Longshore Switch - #18548 Prairieland Switch 345kV Ckt 1FIS Requested07/01/2029
Crater BESSBESS310Tap 345 kV Rockhound Switch (10062) – Prong Moss Switch (10057) ckt 1FIS Requested05/01/2029
Bhalu StorageBESS206Tap 138kV Bulldog (#23833) – Elbow (#23834)FIS Requested04/21/2028
Les Energy StorageBESS205Tap 138 kV 1326 Stanton East – 11324 Leatherwood PodFIS Approved04/30/2028
Midland Energy StorageBESS205Tap 345kV 10057 Prong Moss Switch - 10062 Rockhound Switch CKT 1FIS Requested06/09/2029
Prospector Energy StorageBESS205Natural Dam 138kV Substation (23836)FIS Requested09/30/2026
Odessa Energy StorageBESS2031058 Longshore 345kVFIS Requested05/01/2029
Rattlesnake Gap Wind SLFWind20010119 Tributary Switch 138 kVFIS Requested06/01/2029
Prairie Blossom StorageBESS122Tap 138kV #1322 Big Spring Switch – #1366 Big Spring CRMWDFIS Requested05/08/2029
Calf Creek StorageBESS103Buffalo 138 kV Substation #23837FIS Requested04/01/2030
Luthor SolarSolar101Tap 138kV 23831 Luther Station – 10032 Little LutherFIS Requested09/25/2027
Ariji BESSBESS100Tap 138kV 1394 GTTYVTAP_8 - 1322 BIGSPRIG_8IA Signed03/31/2029
PRI SolarSolar64The 345 kV Falcon Seaboard (#1025) substation; OncorFIS Requested01/31/2027
Silver Hills WindpowerWind5410066 Prong Moss Switch 138kVScreening06/01/2029
Elbow Creek repowerWind01058 Longshore 345kVSync Approved03/31/2027
Rattlesnake Gap Solar SLFSolar010119 Tributary Switch 138 kVFIS Requested06/01/2029
Rattlesnake Gap Storage SLFBESS010119 Tributary Switch 138 kVFIS Requested06/01/2029

For residents and landowners

What power projects are planned in Howard County?
ERCOT's October 2026 report lists 17 active projects in Howard County totalling 2,480 MW. The table on this page lists each one with its fuel type, size, substation and stage.
Where do these projects connect to the grid?
Each project names a point of interconnection, usually a substation or a tap on a transmission line. Land near those points is where developers look for sites.
What does "IA Signed" mean?
The developer has signed an interconnection agreement with the transmission owner. It is one of the strongest signs in the queue that a project may be built, though projects can still withdraw.
When would construction start?
Usually 12 to 24 months before the projected commercial operation date (COD). CODs often move later; each project page shows how many times its COD has changed.
Does a project in the queue mean it will be built?
No. Many queued projects are never built. The queue shows requests to connect, not approved construction. County permits, tax agreements and financing are separate steps.