ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
28INR0419 · Solar · Howard County

PRI Solar

PRI Solar is a 64 MW solar project in Howard County, Texas, connecting at The 345 kV Falcon Seaboard (#1025) substation; Oncor. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 01/31/2027.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
28INR0419
Capacity
64 MW
Fuel
Solar (PV)
Interconnecting entity
BHER Power Resources, Inc.
Projected COD
01/31/2027
Entered queue
07/29/2025
ERCOT zone
WEST
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 07/29/2025
    Entered the queue with 64 MW, projected COD 01/31/2027
  • 07/29/2025
    Screening → FIS Requested

Other projects at this substation

No other projects at this substation.