LoneStarGrid
ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
Substation / point of interconnection ยท Howard County

The 345 kV Falcon Seaboard (#1025) substation; Oncor

1 active project totalling 64 MW is queued to connect at The 345 kV Falcon Seaboard (#1025) substation; Oncor in Howard County, Texas, according to ERCOT's October 2026 report.

Active capacity
64 MW
queued at this substation
Active projects
1
1 project ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
345 kV
read from the name

Projects at this substation

INRProjectFuelMWStageCODDelays
28INR0419PRI SolarSolar64FIS Requested01/31/20270