LoneStarGrid
ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
25INR0143 · BESS · Howard County

Ariji BESS

Ariji BESS is a 100 MW battery storage project in Howard County, Texas, connecting at Tap 138kV 1394 GTTYVTAP_8 - 1322 BIGSPRIG_8. ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 03/31/2029.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
25INR0143
Capacity
100 MW
Fuel
BESS (BA)
Interconnecting entity
Ariji BESS, LLC
Projected COD
03/31/2029
Entered queue
09/15/2022
ERCOT zone
WEST
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 08/01/2025
    FIS Approved → IA Signed
  • 03/03/2025
    FIS Requested → FIS Approved
  • 06/09/2023
    Screening → FIS Requested
  • 09/15/2022
    Entered the queue with 100 MW, projected COD 03/31/2029

Other projects at this substation

No other projects at this substation.