Midland Energy Storage
Midland Energy Storage is a 205 MW battery storage project in Howard County, Texas, connecting at Tap 345kV 10057 Prong Moss Switch - 10062 Rockhound Switch CKT 1. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 06/09/2029.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 25INR0629
- Capacity
- 205 MW
- Fuel
- BESS (BA)
- County
- Howard County
- Interconnecting entity
- Midland Energy Storage LLC
- Projected COD
- 06/09/2029
- Entered queue
- 03/26/2024
- ERCOT zone
- WEST
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 03/26/2024Entered the queue with 205 MW, projected COD 06/09/2029
- 03/26/2024Screening → FIS Requested