ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
25INR0106 · Solar · Howard County

Luthor Solar

Luthor Solar is a 101 MW solar project in Howard County, Texas, connecting at Tap 138kV 23831 Luther Station – 10032 Little Luther. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 09/25/2027.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
25INR0106
Capacity
101 MW
Fuel
Solar (PV)
Interconnecting entity
TREX US Luthor LLC
Projected COD
09/25/2027
Entered queue
06/27/2022
ERCOT zone
WEST
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 04/28/2023
    Screening → FIS Requested
  • 06/27/2022
    Entered the queue with 101 MW, projected COD 09/25/2027

Other projects at this substation

No other projects at this substation.