27INR0323 · BESS · Howard County

Prairie Blossom Storage

Prairie Blossom Storage is a 122 MW battery storage project in Howard County, Texas, connecting at Tap 138kV #1322 Big Spring Switch – #1366 Big Spring CRMWD. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 05/08/2029.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
27INR0323
Capacity
122 MW
Fuel
BESS (BA)
Interconnecting entity
Prairie Blossom Storage, LLC
Projected COD
05/08/2029
Entered queue
10/07/2024
ERCOT zone
WEST
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 10/07/2024
    Entered the queue with 122 MW, projected COD 05/08/2029
  • 10/07/2024
    Screening → FIS Requested

Other projects at this substation

No other projects at this substation.