LoneStarGrid
ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
Counties / Texas

Haskell County power projects

Haskell County, Texas has 17 active power projects totalling 3,976 MW in ERCOT's interconnection queue as of the October 2026 report. Solar is the largest share at 2,301 MW (58%). The largest single project is Grasshopper Solar (408 MW solar). 9 projects have signed an interconnection agreement or reached a later stage. 2 projects in the county are listed as withdrawn or cancelled.

Active projects
17
4.0 GW capacity
IA signed or later
9
53% of active projects
Withdrawn or cancelled
2
listed by ERCOT
Changes tracked
0
since Sep 2026

Changes in Haskell County

No changes in the reports compared so far.

All projects

ProjectFuelMWSubstationStageCOD
Grasshopper SolarSolar408Smoky Hill 345kV Sub (Bus #6104) Locational coordinates : 33.34414; 99.624637FIS Requested10/01/2028
Max 4 WindWind353Tap 345 kV Gauss7D (Bus# 60703) to Quasar7A (Bus# 60712) Transmission LineFIS Requested08/31/2029
Briggs StorageBESS336tap 345kV 60515 Clear Crossing - 60507 PenduloIA Signed04/15/2028
Briggs SolarSolar324tap 345kV 60515 Clear Crossing - 60507 PenduloIA Signed04/15/2028
Solace StorageBESS322tap 345kV 1430 Graham - 1048 TonkawasSync Approved09/01/2026
Quantum StorageBESS32260089 Kilby Switching Station 345kVSync Approved09/01/2026
Quantum SolarSolar32260089 Kilby Station 345kVSync Approved09/01/2026
Solace SolarSolar322tap 345kV 1430 Graham - 1048 TonkawasSync Approved09/01/2026
Blue Spring SolarSolar301#60515 Clear Crossing 345 kVFIS Requested10/28/2028
Rubicon Alpha WindWind22360507 pendulo7A 345kVIA Signed07/31/2027
Inertia SolarSolar202tap 345kV 60515 Clear Crossing - 6104 Smoky HillIA Signed03/31/2029
Millers Branch Solar IIISolar133Tap 345kV 60703 Gauss - 60514 Clear Crossing (60712 QUASAR)Sync Approved10/01/2026
DMF Sagerton Solar SLFSolar126Tap 138kV 6158 Aspermont – 6161 Paint CreekFIS Requested12/15/2028
Journey SolarSolar125Tap 138kV Paint Creek 6161 - Aspermont 6158FIS Requested09/14/2027
Rolling Plains BESSBESS1206104 SMOKY HILL 345kVFIS Requested06/30/2028
Lueders SolarSolar40Tap 138kV 6161 Paint Creek - 6200 Ft PhantomFIS Requested12/31/2029
DMF Sagerton Storage SLFBESS0Tap 138kV 6158 Aspermont – 6161 Paint CreekFIS Requested12/15/2028
Rubicon Echo WindWind228Not listedWithdrawnn/a
Inertia BESS 2BESS101Not listedWithdrawnn/a

For residents and landowners

What power projects are planned in Haskell County?
ERCOT's October 2026 report lists 17 active projects in Haskell County totalling 3,976 MW. The table on this page lists each one with its fuel type, size, substation and stage.
Where do these projects connect to the grid?
Each project names a point of interconnection, usually a substation or a tap on a transmission line. Land near those points is where developers look for sites.
What does "IA Signed" mean?
The developer has signed an interconnection agreement with the transmission owner. It is one of the strongest signs in the queue that a project may be built, though projects can still withdraw.
When would construction start?
Usually 12 to 24 months before the projected commercial operation date (COD). CODs often move later; each project page shows how many times its COD has changed.
Does a project in the queue mean it will be built?
No. Many queued projects are never built. The queue shows requests to connect, not approved construction. County permits, tax agreements and financing are separate steps.