ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
26INR0501 · BESS · Haskell County

Rolling Plains BESS

Rolling Plains BESS is a 120 MW battery storage project in Haskell County, Texas, connecting at 6104 SMOKY HILL 345kV. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 06/30/2028.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
26INR0501
Capacity
120 MW
Fuel
BESS (BA)
Interconnecting entity
Haskell County BESS LLC
Projected COD
06/30/2028
Entered queue
08/16/2024
ERCOT zone
WEST
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 10/21/2024
    Screening → FIS Requested
  • 08/16/2024
    Entered the queue with 120 MW, projected COD 06/30/2028