LoneStarGrid
ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
26INR0310 · BESS · Haskell County

Quantum Storage

Quantum Storage is a 322 MW battery storage project in Haskell County, Texas, connecting at 60089 Kilby Switching Station 345kV. ERCOT's October 2026 report shows it at the Sync Approved stage with a projected commercial operation date of 09/01/2026.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
26INR0310
Capacity
322 MW
Fuel
BESS (BA)
Interconnecting entity
IP Quantum II BESS, LLC
Projected COD
09/01/2026
Entered queue
10/26/2023
ERCOT zone
WEST
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 04/10/2026
    Energization Approved → Sync Approved
  • 03/26/2026
    IA Signed → Energization Approved
  • 06/16/2025
    FIS Requested → FIS Approved
  • 02/22/2024
    Screening → FIS Requested
  • 10/26/2023
    Entered the queue with 322 MW, projected COD 09/01/2026
  • 10/26/2023
    FIS Approved → IA Signed

Other projects at this substation

No other projects at this substation.