ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
21INR0207 · Solar · Haskell County

Quantum Solar

Quantum Solar is a 322 MW solar project in Haskell County, Texas, connecting at 60089 Kilby Station 345kV. ERCOT's October 2026 report shows it at the Sync Approved stage with a projected commercial operation date of 09/01/2026.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
21INR0207
Capacity
322 MW
Fuel
Solar (PV)
Interconnecting entity
IP QUANTUM II, LLC
Projected COD
09/01/2026
Entered queue
09/27/2018
ERCOT zone
WEST
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 04/10/2026
    Energization Approved → Sync Approved
  • 03/06/2026
    IA Signed → Energization Approved
  • 06/16/2025
    FIS Requested → FIS Approved
  • 10/26/2023
    FIS Approved → IA Signed
  • 11/07/2018
    Screening → FIS Requested
  • 09/27/2018
    Entered the queue with 322 MW, projected COD 09/01/2026

Other projects at this substation

No other projects at this substation.