LoneStarGrid
ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
26INR0146 · Solar · Haskell County

DMF Sagerton Solar SLF

DMF Sagerton Solar SLF is a 126 MW solar project in Haskell County, Texas, connecting at Tap 138kV 6158 Aspermont – 6161 Paint Creek. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 12/15/2028.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
26INR0146
Capacity
126 MW
Fuel
Solar (PV)
Interconnecting entity
Double Mountain Fork LLC
Projected COD
12/15/2028
Entered queue
07/24/2023
ERCOT zone
WEST
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 07/24/2023
    Entered the queue with 126 MW, projected COD 12/15/2028
  • 07/24/2023
    Screening → FIS Requested

Other projects at this substation

DMF Sagerton Storage SLFBESS0 MWFIS Requested