Inertia Solar is a 202 MW solar project in Haskell County, Texas, connecting at tap 345kV 60515 Clear Crossing - 6104 Smoky Hill. ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 03/31/2029.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
22INR0374
Capacity
202 MW
Fuel
Solar (PV)
Interconnecting entity
Inertia Solar Project, LLC
Projected COD
03/31/2029
Entered queue
10/13/2020
ERCOT zone
WEST
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 05/10/2023
    FIS Requested → IA Signed
  • 10/13/2020
    Entered the queue with 202 MW, projected COD 03/31/2029
  • 10/13/2020
    Screening → FIS Requested