24INR0125 · Solar · Haskell County

Grasshopper Solar

Grasshopper Solar is a 408 MW solar project in Haskell County, Texas, connecting at Smoky Hill 345kV Sub (Bus #6104) Locational coordinates : 33.34414; 99.624637. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 10/01/2028.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
24INR0125
Capacity
408 MW
Fuel
Solar (PV)
Interconnecting entity
Grasshopper Solar LLC
Projected COD
10/01/2028
Entered queue
09/22/2021
ERCOT zone
WEST
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 09/22/2021
    Entered the queue with 408 MW, projected COD 10/01/2028
  • 09/22/2021
    Screening → FIS Requested

Other projects at this substation

No other projects at this substation.