LoneStarGrid
ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
Counties / Texas

Comanche County power projects

Comanche County, Texas has 8 active power projects totalling 2,446 MW in ERCOT's interconnection queue as of the October 2026 report. Battery storage is the largest share at 1,781 MW (73%). The largest single project is Comanche BESS (614 MW battery storage). 4 projects have signed an interconnection agreement or reached a later stage. 3 projects in the county are listed as withdrawn or cancelled.

Active projects
8
2.4 GW capacity
IA signed or later
4
50% of active projects
Withdrawn or cancelled
3
listed by ERCOT
Changes tracked
4
since Sep 2026

Changes in Comanche County

COD change
10/01/2026
Lamkin Solar · Solar · Comanche County
Projected COD moved 08/08/2027 → 11/08/2027. Delay #1 for this project.
+3 mo
Stage change
09/17/2026
Darkwood Solar · Solar · Comanche County
Moved from FIS Requested to FIS Approved.
FIS Approved
Withdrawn
09/04/2026
Saddle Horn Station BESS SLF · BESS · Comanche County
Listed as inactive by ERCOT.
−177 MW
Withdrawn
09/04/2026
Saddle Horn Station Solar SLF · Solar · Comanche County
Listed as inactive by ERCOT.
−175 MW

All projects

For residents and landowners

What power projects are planned in Comanche County?
ERCOT's October 2026 report lists 8 active projects in Comanche County totalling 2,446 MW. The table on this page lists each one with its fuel type, size, substation and stage.
Where do these projects connect to the grid?
Each project names a point of interconnection, usually a substation or a tap on a transmission line. Land near those points is where developers look for sites.
What does "IA Signed" mean?
The developer has signed an interconnection agreement with the transmission owner. It is one of the strongest signs in the queue that a project may be built, though projects can still withdraw.
When would construction start?
Usually 12 to 24 months before the projected commercial operation date (COD). CODs often move later; each project page shows how many times its COD has changed.
Does a project in the queue mean it will be built?
No. Many queued projects are never built. The queue shows requests to connect, not approved construction. County permits, tax agreements and financing are separate steps.