24INR0157 · BESS · Comanche County
Merope BESS
Merope BESS is a 402 MW battery storage project in Comanche County, Texas, connecting at 345 kV Corn Trail Switch Substation (#11441). ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 03/01/2028.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 24INR0157
- Capacity
- 402 MW
- Fuel
- BESS (BA)
- County
- Comanche County
- Interconnecting entity
- BRP Merope BESS LLC
- Projected COD
- 03/01/2028
- Entered queue
- 12/03/2021
- ERCOT zone
- NORTH
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 12/03/2021Entered the queue with 402 MW, projected COD 03/01/2028
- 12/03/2021Screening → FIS Requested