ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
27INR0050 · BESS · Comanche County

Darkwood BESS

Darkwood BESS is a 150 MW battery storage project in Comanche County, Texas, connecting at Tap 345KV 1900 Comanche Peak - 1440 Comanche Switch. ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 07/01/2028.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
27INR0050
Capacity
150 MW
Fuel
BESS (BA)
Interconnecting entity
Mustang Creek Solar, LLC
Projected COD
07/01/2028
Entered queue
06/07/2023
ERCOT zone
NORTH
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 11/05/2025
    FIS Approved → IA Signed
  • 07/29/2025
    FIS Requested → FIS Approved
  • 10/31/2023
    Screening → FIS Requested
  • 06/07/2023
    Entered the queue with 150 MW, projected COD 07/01/2028

Other projects at this substation