27INR0050 · BESS · Comanche County
Darkwood BESS
Darkwood BESS is a 150 MW battery storage project in Comanche County, Texas, connecting at Tap 345KV 1900 Comanche Peak - 1440 Comanche Switch. ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 07/01/2028.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 27INR0050
- Capacity
- 150 MW
- Fuel
- BESS (BA)
- County
- Comanche County
- Interconnecting entity
- Mustang Creek Solar, LLC
- Projected COD
- 07/01/2028
- Entered queue
- 06/07/2023
- ERCOT zone
- NORTH
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 11/05/2025FIS Approved → IA Signed
- 07/29/2025FIS Requested → FIS Approved
- 10/31/2023Screening → FIS Requested
- 06/07/2023Entered the queue with 150 MW, projected COD 07/01/2028