22INR0237 · Solar · Comanche County

Dragan Solar

Dragan Solar is a 411 MW solar project in Comanche County, Texas, connecting at 1440 Comanche 345kV. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 09/15/2027.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
22INR0237
Capacity
411 MW
Fuel
Solar (PV)
Interconnecting entity
Hecate Comanche Solar LLC
Projected COD
09/15/2027
Entered queue
08/23/2019
ERCOT zone
NORTH
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 08/23/2019
    Entered the queue with 411 MW, projected COD 09/15/2027
  • 08/23/2019
    Screening → FIS Requested

Other projects at this substation

Dragan StorageBESS408 MWFIS Requested