ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
Substation / point of interconnection ยท Comanche County

1440 Comanche 345kV

2 active projects totalling 819 MW are queued to connect at 1440 Comanche 345kV in Comanche County, Texas, according to ERCOT's October 2026 report.

Active capacity
819 MW
queued at this substation
Active projects
2
2 projects ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
345 kV
read from the name

Projects at this substation

INRProjectFuelMWStageCODDelays
22INR0237Dragan SolarSolar411FIS Requested09/15/20270
22INR0400Dragan StorageBESS408FIS Requested03/31/20300