ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
22INR0220 · Solar · Comanche County

Lamkin Solar

COD delayed 1×

Lamkin Solar is a 102 MW solar project in Comanche County, Texas, connecting at tap 69kV 258 Hamilton - 273 Gustine. ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 11/08/2027. Its projected COD has been pushed back 1 time in the reports compared.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
22INR0220
Capacity
102 MW
Fuel
Solar (PV)
Interconnecting entity
Commanche Solar, LLC
Projected COD
11/08/2027
Entered queue
06/24/2019
ERCOT zone
NORTH
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 10/01/2026
    Projected COD moved 08/08/2027 → 11/08/2027 (+3 months)
  • 03/06/2025
    FIS Approved → IA Signed
  • 07/11/2022
    FIS Requested → FIS Approved
  • 03/13/2020
    Screening → FIS Requested
  • 06/24/2019
    Entered the queue with 102 MW, projected COD 08/08/2027