Counties / Texas
Bee County power projects
Bee County, Texas has 12 active power projects totalling 1,839 MW in ERCOT's interconnection queue as of the October 2026 report. Solar is the largest share at 875 MW (48%). The largest single project is Argenta Solar (310 MW solar). 6 projects have signed an interconnection agreement or reached a later stage. 0 projects in the county are listed as withdrawn or cancelled.
Active projects
12
1.8 GW capacity
IA signed or later
6
50% of active projects
Withdrawn or cancelled
0
listed by ERCOT
Changes tracked
4
since Sep 2026
Changes in Bee County
COD change
10/01/2026
Foxtrot Wind · Wind · Bee County
Projected COD moved 08/31/2026 → 12/31/2026. Delay #1 for this project.
+4 mo
COD change
10/01/2026
BumbleBee Solar · Solar · Bee County
Projected COD moved 07/01/2027 → 03/01/2031. Delay #1 for this project.
+44 mo
COD change
10/01/2026
Abeja Solar Farm · Solar · Bee County
Projected COD moved 09/08/2028 → 06/07/2029. Delay #1 for this project.
+9 mo
COD change
10/01/2026
Honeycomb Solar SLF · Solar · Bee County
Projected COD moved 12/29/2026 → 02/27/2027. Delay #1 for this project.
+2 mo
All projects
| Project | Fuel | MW | Substation | Stage | COD |
|---|---|---|---|---|---|
| Argenta Solar | Solar | 310 | Tap 345kV 8689 Tango - 8606 Goddard | IA Signed | 06/30/2028 |
| Foxtrot Wind | Wind | 268 | AEP 88689 Tango 345kV station | Sync Approved | 12/31/2026 |
| Sparta BESS | BESS | 251 | 88690 SPTPOI7A 345kV | Screening | 12/31/2029 |
| BumbleBee Solar | Solar | 201 | Tap 345kV 5725 PawneeSW5 - 8689 Tango | FIS Requested | 03/01/2031 |
| Abeja Solar Farm | Solar | 201 | Tap 345kV 8012 PALADIO7A - 8689 TANGO7A | IA Signed | 06/07/2029 |
| Argenta Storage | BESS | 192 | Tap 345kV 8689 Tango - 8606 Goddard | IA Signed | 06/30/2028 |
| Spinner Energy Storage | BESS | 126 | 8196 Poesta Substation 138kV | FIS Approved | 07/10/2029 |
| Myers Solar | Solar | 102 | 8629 Baez 69 kV | FIS Requested | 05/22/2028 |
| Myers Storage | BESS | 76 | 8629 Baez 69 kV | FIS Requested | 05/22/2028 |
| Honeycomb Solar SLF | Solar | 61 | 69 kV Tynan Substation (#8107) | IA Signed | 02/27/2027 |
| Orchard Ray BESS | BESS | 52 | 8590 Tuleta 138kV | FIS Requested | 05/01/2027 |
| Honeycomb Storage SLF | BESS | 0 | 69 kV Tynan Substation (#8107) | IA Signed | 05/11/2027 |
For residents and landowners
- What power projects are planned in Bee County?
- ERCOT's October 2026 report lists 12 active projects in Bee County totalling 1,839 MW. The table on this page lists each one with its fuel type, size, substation and stage.
- Where do these projects connect to the grid?
- Each project names a point of interconnection, usually a substation or a tap on a transmission line. Land near those points is where developers look for sites.
- What does "IA Signed" mean?
- The developer has signed an interconnection agreement with the transmission owner. It is one of the strongest signs in the queue that a project may be built, though projects can still withdraw.
- When would construction start?
- Usually 12 to 24 months before the projected commercial operation date (COD). CODs often move later; each project page shows how many times its COD has changed.
- Does a project in the queue mean it will be built?
- No. Many queued projects are never built. The queue shows requests to connect, not approved construction. County permits, tax agreements and financing are separate steps.