LoneStarGrid
ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
27INR0372 · Solar · Bee County

Abeja Solar Farm

COD delayed 1×

Abeja Solar Farm is a 201 MW solar project in Bee County, Texas, connecting at Tap 345kV 8012 PALADIO7A - 8689 TANGO7A. ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 06/07/2029. Its projected COD has been pushed back 1 time in the reports compared.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
27INR0372
Capacity
201 MW
Fuel
Solar (PV)
Interconnecting entity
Abeja Solar Farm LLC
Projected COD
06/07/2029
Entered queue
12/09/2024
ERCOT zone
SOUTH
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 10/01/2026
    Projected COD moved 09/08/2028 → 06/07/2029 (+9 months)
  • 12/16/2025
    FIS Requested → IA Signed
  • 12/09/2024
    Entered the queue with 201 MW, projected COD 09/08/2028
  • 12/09/2024
    Screening → FIS Requested