27INR0372 · Solar · Bee County
Abeja Solar Farm
COD delayed 1×
Abeja Solar Farm is a 201 MW solar project in Bee County, Texas, connecting at Tap 345kV 8012 PALADIO7A - 8689 TANGO7A. ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 06/07/2029. Its projected COD has been pushed back 1 time in the reports compared.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 27INR0372
- Capacity
- 201 MW
- Fuel
- Solar (PV)
- Substation
- Tap 345kV 8012 PALADIO7A - 8689 TANGO7A
- County
- Bee County
- Interconnecting entity
- Abeja Solar Farm LLC
- Projected COD
- 06/07/2029
- Entered queue
- 12/09/2024
- ERCOT zone
- SOUTH
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 10/01/2026Projected COD moved 09/08/2028 → 06/07/2029 (+9 months)
- 12/16/2025FIS Requested → IA Signed
- 12/09/2024Entered the queue with 201 MW, projected COD 09/08/2028
- 12/09/2024Screening → FIS Requested
Other projects at this substation
No other projects at this substation.