22INR0559 · Solar · Bee County

Honeycomb Solar SLF

COD delayed 1×

Honeycomb Solar SLF is a 61 MW solar project in Bee County, Texas, connecting at 69 kV Tynan Substation (#8107). ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 02/27/2027. Its projected COD has been pushed back 1 time in the reports compared.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
22INR0559
Capacity
61 MW
Fuel
Solar (PV)
Interconnecting entity
Honeycomb Solar, LLC
Projected COD
02/27/2027
Entered queue
11/02/2021
ERCOT zone
SOUTH
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 10/01/2026
    Projected COD moved 12/29/2026 → 02/27/2027 (+2 months)
  • 03/28/2025
    FIS Requested → FIS Approved
  • 05/01/2023
    FIS Approved → IA Signed
  • 11/02/2021
    Entered the queue with 61 MW, projected COD 12/29/2026
  • 11/02/2021
    Screening → FIS Requested

Other projects at this substation

Honeycomb Storage SLFBESS0 MWIA Signed