23INR0392 · BESS · Bee County
Honeycomb Storage SLF
Honeycomb Storage SLF is a 0 MW battery storage project in Bee County, Texas, connecting at 69 kV Tynan Substation (#8107). ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 05/11/2027.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 23INR0392
- Capacity
- 0 MW
- Fuel
- BESS (BA)
- Substation
- 69 kV Tynan Substation (#8107)
- County
- Bee County
- Interconnecting entity
- Honeycomb BESS, LLC
- Projected COD
- 05/11/2027
- Entered queue
- 11/02/2021
- ERCOT zone
- SOUTH
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 03/28/2025FIS Requested → FIS Approved
- 05/01/2023FIS Approved → IA Signed
- 11/02/2021Entered the queue with 0 MW, projected COD 05/11/2027
- 11/02/2021Screening → FIS Requested
Other projects at this substation
| Honeycomb Solar SLF | Solar | 61 MW | IA Signed |