BumbleBee Solar

COD delayed 1×

BumbleBee Solar is a 201 MW solar project in Bee County, Texas, connecting at Tap 345kV 5725 PawneeSW5 - 8689 Tango. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 03/01/2031. Its projected COD has been pushed back 1 time in the reports compared.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
26INR0412
Capacity
201 MW
Fuel
Solar (PV)
Interconnecting entity
BumbleBee Solar Farm LLC
Projected COD
03/01/2031
Entered queue
02/26/2024
ERCOT zone
SOUTH
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 10/01/2026
    Projected COD moved 07/01/2027 → 03/01/2031 (+44 months)
  • 02/26/2024
    Entered the queue with 201 MW, projected COD 07/01/2027
  • 02/26/2024
    Screening → FIS Requested

Other projects at this substation

No other projects at this substation.