Orchard Ray BESS is a 52 MW battery storage project in Bee County, Texas, connecting at 8590 Tuleta 138kV. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 05/01/2027.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 25INR0394
- Capacity
- 52 MW
- Fuel
- BESS (BA)
- Substation
- 8590 Tuleta 138kV
- County
- Bee County
- Interconnecting entity
- Pettus BESS
- Projected COD
- 05/01/2027
- Entered queue
- 05/31/2023
- ERCOT zone
- SOUTH
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 05/31/2023Entered the queue with 52 MW, projected COD 05/01/2027
- 05/31/2023Screening → FIS Requested