LoneStarGrid
ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
25INR0394 · BESS · Bee County

Orchard Ray BESS

Orchard Ray BESS is a 52 MW battery storage project in Bee County, Texas, connecting at 8590 Tuleta 138kV. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 05/01/2027.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
25INR0394
Capacity
52 MW
Fuel
BESS (BA)
Interconnecting entity
Pettus BESS
Projected COD
05/01/2027
Entered queue
05/31/2023
ERCOT zone
SOUTH
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 05/31/2023
    Entered the queue with 52 MW, projected COD 05/01/2027
  • 05/31/2023
    Screening → FIS Requested

Other projects at this substation

No other projects at this substation.