ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
Counties / Texas

Starr County power projects

Starr County, Texas has 21 active power projects totalling 4,511 MW in ERCOT's interconnection queue as of the October 2026 report. Solar is the largest share at 2,344 MW (52%). The largest single project is Half Moon Solar (512 MW solar). 8 projects have signed an interconnection agreement or reached a later stage. 1 project in the county is listed as withdrawn or cancelled.

Active projects
21
4.5 GW capacity
IA signed or later
8
38% of active projects
Withdrawn or cancelled
1
listed by ERCOT
Changes tracked
3
since Sep 2026

Changes in Starr County

New
10/01/2026
Mandolin Solar III SLF · Solar · Starr County
Entered the queue at Tap 345kV 80355 Del Sol - 80227 Rapido. Projected COD 06/15/2029.
+250 MW
COD change
10/01/2026
Diamondback solar · Solar · Starr County
Projected COD moved 05/31/2028 → 04/29/2028. Moved earlier.
-1 mo
MW change
10/01/2026
Diamondback solar · Solar · Starr County
Requested capacity reduced.
204 → 200 MW

All projects

ProjectFuelMWSubstationStageCOD
Half Moon SolarSolar512#80231 Pronto 345kVIA Signed07/01/2029
Sendero SolarSolar503Tap 345kV 80079 Cruce - 80355 Del SolScreening05/15/2029
Mandolin Solar II SLFSolar304Tap 345kV 80355 Del Sol - 80227 RapidoFIS Requested06/15/2029
Bullring Wind 2Wind304Tap 345 kV 80355 DelSol7A - 80079 Cruce Ckt 1IA Signed06/30/2028
Bullring Wind 1Wind304Tap 345 kV 80355 DelSol7A - 80079 Cruce Ckt 1IA Signed06/30/2028
Mandolin Solar SLFSolar300Tap 345kV 80355 Del Sol - 80227 RapidoFIS Requested06/15/2029
Fierce River BESSBESS284Tapping the 345 kV Line from Del Sol (Bus# 80355) to Frontera (Bus# 80119) ckt 1FIS Requested02/22/2029
Mandolin Solar III SLFSolar250Tap 345kV 80355 Del Sol - 80227 RapidoFIS Requested06/15/2029
Bessie StorageBESS211Charly Egner Substation Tap 345kV 80355 Del Sol - 80368 LV4 BridgeFIS Requested09/28/2029
Mesteno WindWind20280355 Del Sol 345kVSync Approved03/01/2027
Diamondback solarSolar20080355 Del Sol 345kVIA Signed04/29/2028
PSE Flores TX StorageBESS200TAP 138KV 8793 RIO GRANDE CITY - 8798 LAGRULLAFIS Requested06/30/2028
PSE Gongora Hill TX StorageBESS200Tap 138kV 8796 Roma – 7870 EscobaresFIS Requested06/30/2028
Bullring Wind 3Wind190Tap 345 kV 80355 DelSol7A - 80079 Cruce Ckt 1IA Signed06/30/2028
Sword SolarSolar137Tap 138 kV 8394 Liston - 8392 BatesFIS Requested02/22/2029
Starr Solar RanchSolar1378795 Roma 138kVSync Approved08/14/2025
Halcon StorageBESS133Tap 138kV 8957 Central Lopeno - 80106 Falcon DamFIS Requested05/15/2028
Bordertown BESSBESS1008796 Roma 138kVIA Signed12/01/2028
Sword BESSBESS40Tap 138 kV 8394 Liston - 8392 BatesFIS Requested02/22/2029
Starr StorageBESS08795 Roma 138kVFIS Requested03/29/2028
Mandolin Storage SLFBESS0Tap 345kV 80355 Del Sol - 80227 RapidoFIS Requested06/15/2029
Diamondback BESSBESS204Not listedWithdrawnn/a

For residents and landowners

What power projects are planned in Starr County?
ERCOT's October 2026 report lists 21 active projects in Starr County totalling 4,511 MW. The table on this page lists each one with its fuel type, size, substation and stage.
Where do these projects connect to the grid?
Each project names a point of interconnection, usually a substation or a tap on a transmission line. Land near those points is where developers look for sites.
What does "IA Signed" mean?
The developer has signed an interconnection agreement with the transmission owner. It is one of the strongest signs in the queue that a project may be built, though projects can still withdraw.
When would construction start?
Usually 12 to 24 months before the projected commercial operation date (COD). CODs often move later; each project page shows how many times its COD has changed.
Does a project in the queue mean it will be built?
No. Many queued projects are never built. The queue shows requests to connect, not approved construction. County permits, tax agreements and financing are separate steps.