LoneStarGrid
ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
23INR0455 · BESS · Starr County

Bessie Storage

Bessie Storage is a 211 MW battery storage project in Starr County, Texas, connecting at Charly Egner Substation Tap 345kV 80355 Del Sol - 80368 LV4 Bridge. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 09/28/2029.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
23INR0455
Capacity
211 MW
Fuel
BESS (BA)
Interconnecting entity
Bessie Energy Storage, LLC
Projected COD
09/28/2029
Entered queue
02/07/2022
ERCOT zone
SOUTH
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 02/07/2022
    Entered the queue with 211 MW, projected COD 09/28/2029
  • 02/07/2022
    Screening → FIS Requested

Other projects at this substation

No other projects at this substation.