26INR0446 · BESS · Starr County
Sword BESS
Sword BESS is a 40 MW battery storage project in Starr County, Texas, connecting at Tap 138 kV 8394 Liston - 8392 Bates. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 02/22/2029.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 26INR0446
- Capacity
- 40 MW
- Fuel
- BESS (BA)
- Substation
- Tap 138 kV 8394 Liston - 8392 Bates
- County
- Starr County
- Interconnecting entity
- Hidalgo Solar LLC
- Projected COD
- 02/22/2029
- Entered queue
- 03/22/2024
- ERCOT zone
- SOUTH
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 11/12/2024Screening → FIS Requested
- 03/22/2024Entered the queue with 40 MW, projected COD 02/22/2029
Other projects at this substation
| Sword Solar | Solar | 137 MW | FIS Requested |