16INR0081 · Wind · Starr County
Mesteno Wind
Mesteno Wind is a 202 MW wind project in Starr County, Texas, connecting at 80355 Del Sol 345kV. ERCOT's October 2026 report shows it at the Sync Approved stage with a projected commercial operation date of 03/01/2027.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 16INR0081
- Capacity
- 202 MW
- Fuel
- Wind (WT)
- Substation
- 80355 Del Sol 345kV
- County
- Starr County
- Interconnecting entity
- Mesteno Windpower, LLC
- Projected COD
- 03/01/2027
- Entered queue
- 12/30/2014
- ERCOT zone
- SOUTH
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 12/12/2019Energization Approved → Sync Approved
- 11/26/2019IA Signed → Energization Approved
- 04/25/2018FIS Approved → IA Signed
- 01/29/2018FIS Requested → FIS Approved
- 12/30/2014Entered the queue with 202 MW, projected COD 03/01/2027
- 12/30/2014Screening → FIS Requested
Other projects at this substation
| Diamondback solar | Solar | 200 MW | IA Signed |