27INR0222 · BESS · Starr County

Fierce River BESS

Fierce River BESS is a 284 MW battery storage project in Starr County, Texas, connecting at Tapping the 345 kV Line from Del Sol (Bus# 80355) to Frontera (Bus# 80119) ckt 1. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 02/22/2029.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
27INR0222
Capacity
284 MW
Fuel
BESS (BA)
Interconnecting entity
Rio Grande Solar LLC
Projected COD
02/22/2029
Entered queue
03/22/2024
ERCOT zone
SOUTH
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 11/12/2024
    Screening → FIS Requested
  • 03/22/2024
    Entered the queue with 284 MW, projected COD 02/22/2029

Other projects at this substation

No other projects at this substation.