Kinney County power projects

Kinney County, Texas has 8 active power projects totalling 709 MW in ERCOT's interconnection queue as of the October 2026 report. Solar is the largest share at 507 MW (71%). The largest single project is Longday Solar SLF (201 MW solar). 0 projects have signed an interconnection agreement or reached a later stage. 2 projects in the county are listed as withdrawn or cancelled.

Active projects
8
0.7 GW capacity
IA signed or later
0
0% of active projects
Withdrawn or cancelled
2
listed by ERCOT
Changes tracked
3
since Sep 2026

Changes in Kinney County

COD change
10/01/2026
Turkey Creek Solar SLF · Solar · Kinney County
Projected COD moved 10/26/2027 → 09/01/2028. Delay #1 for this project.
+10 mo
COD change
10/01/2026
Turkey Creek Battery Energy Storage System SLF · BESS · Kinney County
Projected COD moved 10/26/2027 → 09/01/2028. Delay #1 for this project.
+10 mo
Withdrawn
09/14/2026
GALVANIC BESS · BESS · Kinney County
Listed as cancelled by ERCOT.
−100 MW

All projects

ProjectFuelMWSubstationStageCOD
Longday Solar SLFSolar201Tap138 kV 8252 Brackettville - 8260 EscondidoFIS Requested12/15/2027
Turkey Creek Solar SLFSolar1817425 ODLASW 138kVFIS Requested09/01/2028
Sugarberry Solar SLFSolar12578255 Pinto Creek 138 kVFIS Requested12/18/2029
Kinney County EnergyBESS101Tap 138kV 8252 Brackett4A - 78255 L_PINTCR8_1YFIS Requested05/15/2027
Las Moras BatteryBESS1018252 Brackett 138kVFIS Requested07/01/2029
Longday BESS SLFBESS0Tap 138 kV 8252 Brackettville - 8260 EscondidoFIS Requested12/15/2027
Turkey Creek Battery Energy Storage System SLFBESS07425 ODLASW 138 kVFIS Requested09/01/2028
Sugarberry Storage SLFBESS078255 Pinto Creek 138 kVFIS Requested12/18/2029
DeSpain Solar ProjectSolar236Not listedWithdrawnn/a
GALVANIC BESSBESS1008252 Bracketville 138kVWithdrawn12/30/2027

For residents and landowners

What power projects are planned in Kinney County?
ERCOT's October 2026 report lists 8 active projects in Kinney County totalling 709 MW. The table on this page lists each one with its fuel type, size, substation and stage.
Where do these projects connect to the grid?
Each project names a point of interconnection, usually a substation or a tap on a transmission line. Land near those points is where developers look for sites.
What does "IA Signed" mean?
The developer has signed an interconnection agreement with the transmission owner. It is one of the strongest signs in the queue that a project may be built, though projects can still withdraw.
When would construction start?
Usually 12 to 24 months before the projected commercial operation date (COD). CODs often move later; each project page shows how many times its COD has changed.
Does a project in the queue mean it will be built?
No. Many queued projects are never built. The queue shows requests to connect, not approved construction. County permits, tax agreements and financing are separate steps.