29INR0252 · BESS · Kinney County
Sugarberry Storage SLF
Sugarberry Storage SLF is a 0 MW battery storage project in Kinney County, Texas, connecting at 78255 Pinto Creek 138 kV. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 12/18/2029.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 29INR0252
- Capacity
- 0 MW
- Fuel
- BESS (BA)
- Substation
- 78255 Pinto Creek 138 kV
- County
- Kinney County
- Interconnecting entity
- EG Sugarberry LLC
- Projected COD
- 12/18/2029
- Entered queue
- 03/26/2026
- ERCOT zone
- SOUTH
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 03/26/2026Entered the queue with 0 MW, projected COD 12/18/2029
- 03/26/2026Screening → FIS Requested
Other projects at this substation
| Sugarberry Solar SLF | Solar | 125 MW | FIS Requested |